Prime Minister to lay Foundation Stone for Delhi-Meerut Expressway



Prime Minister to lay Foundation Stone for Delhi-Meerut Expressway 
Prime Minister Shri Narendra Modi will lay the foundation stone for the construction of 74 Km long Delhi-Dasna-Meerut 14 lane Expressway and upgradation of 22 Km long Dasna-Hapur section of NH-24, at Institutional Area, Plot No A-33, Sector -62, Noida, at 12 Noon on Thursday ,the 31st of December  2015. Uttar Pradesh Governor Shri Ram Naik, Union Minister of Road Transport & Highways Shri Nitin Gadkari, Union Minister of Science & Technology and Earth Sciences Shri Harsh Vardhan, MoS, Culture and Tourism(I/C) and Civil Aviation Dr Mahesh Sharma, MoS Statistics & Programme Implementation (I/C), External Affairs and Overseas Indian Affairs General V.K.Singh and MoS  Road Transport and Shipping Shri P. Radhakrishnan will also be present on the occasion.

Union Minister of Road Transport & Highways Shri Nitin Gadkari informed that the above project will cost Rs 7566 Crore  and will include the following three components :
·         DME Phase-I - Construction of 28 km long 14 lane Delhi-Dasna section of Delhi-Meerut Expressway, costing Rs 2869 Crore
·         DME Phase II – Construction of 46 km long, 6 lane Dasna-Meerut section of Delhi-Meerut Expressway, costing Rs 3575 Crore
·         6- laning of 22 km long Dasna-Hapur section of NH -24 costing Rs 1122 Crore.
There is an urgent need for an expressway between Delhi and Meerut because NH-  58, the only existing link between the two places is heavily congested with traffic. The alignment of Delhi-Meerut Express will start from Nizammudin Bridge [T point km 00.000] from Delhi and will continue on existing NH – 24 upto Dasna [km 30.38].  From Dasna there will be completely a new alignment upto Meerut.  The alignment will terminate on inner ring road/ Meerut bypass near Railway crossing [km 66] at Meerut. 

            The project constitutes of 4-packages as detailed under:

Package No.
Description of Packages
I
Nizamuddin Bridge to UP Border (Km 0.000 to Km 8.360)
II
UP Border to Dasna (Km 8.360 to Km 27.500)
III
Dasna to Hapur (Km 27.500 to Km 49.923)
IV
New Alignment of Delhi Meerut Expressway from Dasna to Meerut (27.500 to 64.552 = 37.052 Km.) & six laning of connector (0.00 to 9.004 = 9.004 Km.)

Bids for the Delhi-Hapur section of NH-24 project in following three packages on new Hybrid Annuity Model have been invited with bid due date as 15.12.2015:


Package No.
Description of Packages
Civil Cost (Rs. In Cr)
I
Nizamuddin Bridge to UP Border (Km 0.000 to Km 8.360)
609.67
II
UP Border to Dasna (Km 8.360 to Km 27.500)
1259.43
III
Dasna to Hapur (Km 27.500 to Km 49.923)
940.50


2809.60


New Alignment of DME from Dasna to Meerut (Km 27.500 to 64.552) & 6-laing of Connector (Km 0.000 to Km 9.004) is also to be taken up after the completion of 90% land acquisition.
Project Features:
Sl. No.
Element
Packages
Total
I
II
III
1
Length (Km)
8.716
19.284
22.270
50.270
2
Lanes
6 lane Expressway, 4+4 lane Highway
NH-24 (3+3)
3
Service Road/Slip Roads (Km)
0
0
41.36
41.36
4
Cycle Tracks (Km)
8.716
19.284
0
28.000
5
Flyovers/Interchanges (Nos.)
4
1
1
6
6
Elevated section (Km)
0
0
4.66
4.66
7
Major Bridges (Nos.)
1
2
1
4
8
Minor Bridges (Nos.)
2
1
7
10
9
Railway Over Bridge (Nos.)
0
1
0
1
10
Vehicular Underpasses (Nos.)
5
12
6
22
11
Pedestrian Underpasses (Nos.)
0
6
1
8

The status of pre construction activities, land acquisition and other details are as follows-  

Package I

Description
Status
 Land acquisition
Total land required        : 83.184 Ha
Land in possession       : 78.444 Ha (94.3%)
Balance to be acquired : 4.74 Ha (To be transferred from Govt. of Delhi/DDA)
MOEF Clearance
Not  Required
Forest Clearance
Forest Clearance is not required. Only tree cutting permission is required . Tree counting is in progress.
GAD of ROB
There is  no ROB

Package II

Description
Status
 Land acquisition
Total land required        : 173.556 Ha
Land in possession       : 173.556 Ha (100%)
Encroachments in Pandav Nagar to be got removed
MOEF Clearance
Not  Required
Forest Clearance
Applications submitted to Forest Deptt. Joint inspection of Ghaziabad district is in progress.
GADs
There is 1 ROB for which the GAD has been submitted to the Railways and approval is under process.

Package III

Description
Status
 Land acquisition
Total land required        : 91.870 Ha
Land in possession       :  91.370 Ha (99.50%)
Balance to be acquired :  0.50 Ha
3A notification: Under Process
MOEF Clearance
Not  Required
Forest Clearance
Applications submitted to Forest Deptt. Joint inspection of district Hapur completed, Meerut & Ghaziabad district in progress.
GAD of ROB
Nil



No comments