CTE’s INSPECTION: VALUE FOR GOVERNMENT MONEY
CTE’s INSPECTION: VALUE FOR GOVERNMENT MONEY
The Chief Technical
Examiner’s Organization works under administrative control of Central Vigilance
Commission. It deals with Technical
matters including technical examination of works undertaken by various organizations, Ministries, Departments and Public Sector
Undertakings etc.
The Public Accounts
Committee, in 1947-48 recommended to set up an inter departmental committee to
examine the question of setting up an independent inspection agency for
Technical examination of expenditure of CPWD works.
The Committee, set up
in May, 1948 recommended introduction of
an organization on the pattern of Chief Technical Examiner and Chief
Surveyor of the works in the CPWD.
Initially, only a
Superintending Surveyor of work organisation was set up under the control of
Chief Engineer, CPWD. The organization
was signed to inspect the all important work, during their progress and after
their completions, undertaken by CPWD.
Public Accounts
Committee, in year 1956 reiterated and pressed for setting up CTE’s
Organisation and Central Government issued formal order for creation of Chief
Technical Examiner’s Cell in the then Ministry of the Work Housing and Supply
in May 1957.
As per recommendation
of Committee on Prevention of Corruption under the Chairmanship of Sh. K.
Santhanam, the jurisdiction of CTE was extended to cover the construction works
undertaken by other Ministries/Departments/Public Sector Undertakings etc. and
CTE’s Organisation was placed under the administrative control of the
Central Vigilance Commission in 1964.
CTE may carry out
Intensive Examination of any work of any magnitude, yet, considering its
limited resources, it generally examines works of larger size only. The quarterly progress reports of all
important works are sent to CTE organization in January, April, July and
October every year by the concerned PSU/Department.,
CTE’s Inspections are
mostly done with prior intimation so that concerned Engineers, Planners,
Designers and the tender accepting authority may clarify their points.
After intensive
examination is carried out by Technical Examiner of CTE’s Organization,
inspection report is sent to Chief Vigilance Officer of concerned
Department/Ministry/PSU.
The report brings out
instances of lapses/irregularities in awarding contract, defective contract
conditions and clauses, overpayment made to the contractor, execution and
acceptance of sub-standard work, infructuous and avoidable expenditure etc.
CTE may also suggest
preventive measures in certain areas as a safeguard against malpractices or
corrupt practices and to plug loopholes in procedure/rules, regulations etc.
In case, where
serious irregularities or negligence are observed, such paras are referred to Chief Vigilance Officer for
detailed investigation.
The defects, pointed
out in CTE’s report, should be removed either by contractor or otherwise (at
the risk and cost of contractor).
Minor irregularities brought in
the report should be got regularized by competent authority after ascertaining
reasons for the same. Preventive
measures may be taken and defaulters may be suitably warned so that such
irregularities do not occur in future.
The CTE’s function
has resulted in recovery of Rs.8.75 crores in year 2000-01 which was more than
the total budget of year 2000-01 of CVC which was of the
order of Rs. 4 crores.
The CTE’s
organization has carried out Intensive Examination of various works at Western
Coalfields Limited in recent past. The
irregularities, which are generally pointed out, in Intensive Examination
Report of CTE are compiled as follows:
·
Press release of NIT should
not be released in anticipation of approval of NIT.
·
Administrative approval, expenditure sanction and approval
of preliminary must be obtained before making detailed estimate.
·
Decision must be taken, for type of foundation to be
adopted during execution, before award of work.
·
Copy of sanctioned estimate must be made available to the
site Engineer.
·
Letter of extension of validity of offer must be obtained
before expiry of validity of tenders to avoid difficulty in case of dispute by
agency.
·
Cutting and overwriting in tenders must be authenticated to
avoid scope of any dispute at later stage.
·
The condition of advancing the progress of one of model
units in completing it in all respect in advance to avoid the recurrence of
same discrepancy/mistakes in all repetitive units should be incorporated in
tender.
·
Letter of acceptance of tender incorporates period of
completion of work excluding rainy-season.
Why the period of completion including rainy season could not be
specified? Period of rainy season should
be prescribed.
·
The item of pile foundation stipulates that bailing out
water if any, met during bore is included in rate of item of boring. Such note has greater financial implication
around 25% of cost of boring. It gives
scope to tenderers to quote higher rate.
It should have been covered under separate item after detailed survey of
site condition.
·
In addition responsibilities of contractor, contractor has to arrange insurance in the name of the
company. It should be ascertained that
necessary insurance cover has been obtained by the agency.
·
Hindrances were recorded on account of non-availability of
cement, labour shortage, machineries, which were responsibility of
contractor. As such hindrances on this
account are not admissible.
·
Sources of receipt of cement, batch number and brand name
of paint and theoretical consumption of paint should be mentioned in the cement
and paint consumption registers to control the actual consumption of these
materials.
·
Number of mandatory tests
are on lower side.
·
Cement concrete cubes are not tested at regular interval of
7 days and 28 days, thus defeating the very purpose of testing concrete cubes.
·
End beam should be provided in sloping roofs.
·
Pinhead glasses are provided in place of Plain sheet glass.
·
Ventilator frame are not of ISI marked.
·
Groove, in plaster at junction of wall and roof, have not
been provided.
·
Size of Tower-bolt
are of lesser length than specified.
·
Thickness of waist slab of staircase was found 110 mm
against 120 mm as specified.
·
Dates are not being put on plasterwork to watch curing of
plaster.
·
Top of parapet had been plastered instead of coping.
·
Half brick wall was provided without reinforcements in railing
and parapet.
·
Plinth protection level was lower than road level in some
of the blocks.
·
There is no system of making part rate payment still, some
items have not been executed fully but paid at full rate and some amount has
been withheld.
·
Proper sequence for providing dado and flooring in W.C. and
bath had not been followed, i.e. dado item has been executed before flooring.
·
The sizes of rails and styles was changed.
·
In one work, species
of wood was found to be `Hollock’
instead of Bijasal as specified in agreement.
·
Weight of holdfast and tie rod should not be included in
the weight of doorframe while making payment as per CPWD specification.
·
Smaller sizes of holdfast have been used for fixing frame
in half brickwork.
·
Manhole are at higher level than the plinth protection and
Manhole covers are too light and size of manhole opening is too small.
·
Date of expiry of chemical has not been mentioned on
anti--termite register.
·
Thickness of marble
used in the work was less than 30 mm as required.
·
Secured advance, on perishable items should not be paid
without obtaining insurance cover.
·
Theoretical consumption of murum, aggregate boulder,
bitumen should be prepared to ascertain that the quantity of materials actually
used are not less than the required theoretically.
·
Floor trap used in building work are of contracted neck
variety which are not permissible.
·
Tack welding has been used in manufacturing of steel window
against continuous flash butt welding.
·
Rawl plug have not been provided at top and bottom member
of steel window.
·
25 mm thick Kota stone has been used in kitchen slab in
place of 25 mm thick Cuddappa stone as specified in agreement.
·
Under coat of cement mortar plaster for providing glazed
tiles had not been roughened and it had been much advanced, which will result
in inadequate bond between tiles and floor.
·
Bed blocks over brickwall under the RCC beam have not been
provided.
·
The acceptability of test result and action taken for
failure of sample in respect of testing of mandatory test of several construction
materials are not being recorded.
·
Glazed tiles are not tested for their specification.
·
No interest fee mobilization advance should be paid to the
contractor.
·
Minimum weight of empty HDPE tank (500 litres) (Exclusive
of man-hole lid & fitting) and the minimum wall thickness of top, bottom
and sides as per IS 10146-1982 are 18.00 kg and 6 mm respectively.
·
Size of kitchen sinks provided are less than the specified
in agreement.
·
Pro-rate progress had not been achieved.
************
Post a Comment